VADODARA - HALOL TOLL ROAD
1. Background
Vadodara Halol Toll Road Company Limited (VHTRL) was promoted by Government of Gujarat (GoG) and Infrastructure Leasing & Financial Services (IL&FS) specifically for the purpose of developing and implementing Vadodara Halol Road Project under Built, Own, Operate and Transfer (BOOT) basis. Annual and Periodic Maintenance (including renewal and overlay) for next 30 years also to be carried out by VHTRL. The construction of Vadodara Halol Toll Road commenced on 1st March 1999 and the project achieved substantial completion on 15th September 2000. The Toll Operations commenced on 24th October 2000. The project has been completed within budgeted cost and time.
2. Management
VHTRL and ALTRL is merged in to GTRICL and its Board of Directors comprises of the following members:
| Government of Gujarat Nominees | |
|
Mr.
S S Rathore |
Principal Secretary, Narmada and water Resources Department |
|
Mr.
A. K. Sharma |
Chief Executive Officer, Gujarat Infrastructure Development Board |
|
Mr.
S.I.Patel |
Secretary, Roads & Buildings Department |
|
Mr.
P. P. Vakharia |
Chief Engineer (SP) & Additional Secretary, Roads & Buildings Department |
|
Mr. R B Pandit |
Officer on Special Duty, Roads & Buildings Department |
| IL&FS Nominees | |
| Mr. Manu Kocher | Executive Director (Finance Op), IL&FS |
| Mr. Ashok Totlani | Advisor-Infrastructure, IL&FS |
| Mr. K. Ramchand | President & CEO, CTNL |
| IDBI nominee | |
| Mr. Y.K.Mankad | IDBI |
| Mr. Mukund Sapre is the Chief Executive Officer of the Company. | |
3. User Charges
GOVERNMENT of GUJARAT
Roads & Buildings Department
Sachivalaya, Gandhinagar
Date: 19/03/2007
No.
1.
The
2.
3.
Now in
|
1 |
2 |
3 |
|
Sr.
|
|
or
Halol
|
|
1. |
Truck, 2 - axles |
90 |
|
2. |
|
60 |
|
3. |
Bus, 2 - axles |
90 |
|
4. |
Light
|
50 |
|
5. |
Cars |
30 |
|
6. |
|
15 |
|
7 |
Two Wheelers |
10 |
4.
The
5.
The Concessionaire is
6.
All users of the
7.
All non - mo
The employees
4. Project Cost
Landed Cost of
the Project : Rs. 160.83 Crores
Construction Cost of the Project : Rs. 119 Crores
5. Salient Features of the Project
•
Widening and strengthening of existing 31.7 Km long road from two lanes to
four lanes divided carriageway and continuous service roads on either
side.
• Construction of new bypasses at village Jarod, Asoj and Baska
• 2 Nos. Main Toll Plazas one Vadodara side and other Halol side at
Km 8+970 and Km 39+750 respectively and one intermediate toll plaza at Savli
– Vaghodia Junction.
• 3 major bridges and 3 minor bridges.
• 7 Nos. Underpasses of size of 5 m x 3 m
• Retro-reflective signboards to improve road safety with
very good riding quality to enhance user comfort.
• Embankment Repairs and Turfing to stabilize the slopes.
• Round-the-clock Highway Patrolling
• 24 hours Ambulance services
• Extensive tree plantation and transplantation of trees.
• Provision of roadside arboriculture and landscaping.
• Provision of bus-bays, bus-stops, passenger shelters and truck lay-bys
along the project road
• Toll Rates are based on road user benefits including savings in Vehicle
Operating Costs, Fuel and Time.
• Smart Card technology is also used for regular users to facilitate
ease of transaction.
6.
Other Details
Independent Engineer : Frischmann & Prabhu (India) Private Limited
Independent Auditor : A. F. Ferguson & Co.
Project Engineer : M/s Lea Associates South Asia Private Limited
Construction Contractor : Joint Venture of M/s Punj Lloyd Ltd. and M/s IRCON International
O & M and
Toll Collection
Contractor
: M/s Punj Lloyd Ltd. (PLL)